TY - GEN
T1 - Applying acoustic pulse reflectometry in a geothermal energy plant
T2 - ASME 2010 Power Conference, POWER 2010
AU - Amir, Noam
AU - Bobrow, Daniel
AU - Pechter, Tal
PY - 2010
Y1 - 2010
N2 - One major type of heat exchanger in geothermal powerplants acts to condense an organic vapor driving the generating turbines. Routine inspection carried out at such a plant in the spring of 2008 detected several leaking tubes in one of the condensers. The condenser consists of 11 banks, each with 284 tubes. The tubes in this condenser are 1" in diameter and 18m in length. A sample of tubes was investigated by a metallurgical laboratory which determined that the failure mechanism was corrosion. This was eventually traced to a faulty maintenance procedure which left water traces after pressure hydro testing. Several NDT methods were considered in order to screen the tubes for leaks, so the unit could be brought up to standard performance levels. Eventually AcousticEye's APR equipment was selected, based on the very short cycle time it offered, which could dramatically shorten plant downtime. After an initial feasibility test of one of the tube banks, the remaining 2840 tubes were inspected in 2 days. Four percent of the tubes were found either leaking or deteriorated above a predefined maximum acceptable damage level (pinholes and tube wall thickness reduction) and plugged. Benefits were prevention of a continued loss of 70 Kg/day of organic fluid (which is not only wasteful but also infringes on environmental legislation) and an increase of 1.5% in plant performance. Based on this experience, the operator decided to adopt APR based inspection as a standard procedure in its plants.
AB - One major type of heat exchanger in geothermal powerplants acts to condense an organic vapor driving the generating turbines. Routine inspection carried out at such a plant in the spring of 2008 detected several leaking tubes in one of the condensers. The condenser consists of 11 banks, each with 284 tubes. The tubes in this condenser are 1" in diameter and 18m in length. A sample of tubes was investigated by a metallurgical laboratory which determined that the failure mechanism was corrosion. This was eventually traced to a faulty maintenance procedure which left water traces after pressure hydro testing. Several NDT methods were considered in order to screen the tubes for leaks, so the unit could be brought up to standard performance levels. Eventually AcousticEye's APR equipment was selected, based on the very short cycle time it offered, which could dramatically shorten plant downtime. After an initial feasibility test of one of the tube banks, the remaining 2840 tubes were inspected in 2 days. Four percent of the tubes were found either leaking or deteriorated above a predefined maximum acceptable damage level (pinholes and tube wall thickness reduction) and plugged. Benefits were prevention of a continued loss of 70 Kg/day of organic fluid (which is not only wasteful but also infringes on environmental legislation) and an increase of 1.5% in plant performance. Based on this experience, the operator decided to adopt APR based inspection as a standard procedure in its plants.
UR - http://www.scopus.com/inward/record.url?scp=80053093241&partnerID=8YFLogxK
U2 - 10.1115/POWER2010-27207
DO - 10.1115/POWER2010-27207
M3 - ???researchoutput.researchoutputtypes.contributiontobookanthology.conference???
AN - SCOPUS:80053093241
SN - 9780791849354
T3 - American Society of Mechanical Engineers, Power Division (Publication) POWER
SP - 431
EP - 434
BT - ASME 2010 Power Conference, POWER 2010
Y2 - 13 July 2010 through 15 July 2010
ER -